ST. CROIX--The Committee of the Whole, chaired by Senate President Myron D. Jackson, met on Wednesday in the Virgin Islands Cardiac Center of the Governor Juan F. Luis Hospital and Medical Center where testimony was given on a Major Coastal Zone Management Permit.

Senators heard from several Limetree Bay Terminals L.L.C. management Executives regarding Major CZM Permit CZX-29-17 for a Single Point Mooring (SPM) to be constructed on the south of St. Croix. The project’s activities will be specifically located seaward of Limetree Bay Terminals, LLC Terminal Plot No. 9 Reclaimed Land, Christiansted.

In his testimony, Jason Gleason, Maine Terminal Pilot and Captain for Limetree Bay Terminals, said as Lead Superintendent in the Marine Department and Project Lead on the SPM Project, Very Large Crude Carriers (VLCCs) are some of the largest vessels in the world often over 1100ft long and 200ft, wide and may have a draft of over 700ft.

He added that historically to call on St. Croix, a VLCC would need to be roughly half loaded, and so, this project will enable their customers to transport crude to and from the facility in full loaded VLCC, offering a much more efficient operation.

According to Gleason, the Limetree Bay SPM will transfer crude oil to and from the facility and with the upgraded crude pumps completed last year, they can load out at approximately 45,000 barrels per hour. He pointed out that, the SPM project has been designed to Oil Companies International Marine Forum (OCIMF); United States Coast Guard (USCG) and American Bureau #56 King Street, Hamilton House, Christiansted, St. Croix 00820 340-773-2424, Fax: 340-712-2397, E-mail: publicaffairs@legvi.org of Shipping (ABS) standard. Furthermore, the entire system is designed to withstand the extreme conditions often found in in the Caribbean region.

Senators, who expressed their concerns as they relate to the project’s impact on the ecosystem, was given assurance by Gleason that after an extensive environmental assessment and re-routing of the project to minimize environmental impact, it was determined that a few corals were still in the pathway of the project.

According to him, these corals will be transplanted well clear of the project by their environmental contractor, Bio Impact. They will also be constructing a man-made reef to provide additional habitat where some of the coral will be transplanted on both the south and north shores of St. Croix in areas already approved by the Department of Planning and Natural Resources (DPNR).

Gleason added that during construction, Bio Impact will be monitoring for turbidity, the effect on wildlife, and any other issues. Moreover, Bioimpact will stop the work immediately if any issues arise, and that they will work with DPNR and the federal government to remedy prior to resumption of construction.

In respect to local employment, Gleason told Senators that many of the materials to construct have been procured and delivered to St. Croix, and with the ratification by the legislature, they will commence construction as soon as possible. The construction phase, he added, will result in employment for laborers, concrete workers, welders, inspectors and painters on St. Croix.

Other testifiers for Limetree Bay Terminals were: Joyce Wakefield, Environmental Specialist; Amy Dempsey, President of Bio Impact; and Jeff Gorman, Engineer, Lloyds Engineers. Senators at Wednesday’s Committee of Whole Hearing were: Senate President, Myron D. Jackson, Vice-President, Rivera-O’Reilly, Jean A. Forde, Neville A. James, Marvin A. Blyden, Dwayne DeGraff, Novelle E. Francis, Jr., Alicia “Chucky” Hansen, Positive T.A. Nelson, Tregenza A. Roach, Sammuel Sanes, Janelle K. Sarauw, Brian A. Smith, and Kurt A. Vialet.

###